Applies to: E4

Unpacking and positioning

Watch the video

YouTube video – When viewing this video, personal data is sent to YouTube, LLC, USA. Privacy statement

Choosing the installation site

The installation site must meet the limit values and requirements in chapter Technical data.

Technical data

Unpacking the machine

  1. Place the transport carton on a surface that can carry the weight.

    • The arrows on the transport position sticker must be pointing upward.

    • You need a free space of at least 47 x 55 x 67 cm / 19 x 22 x 26 in (W/D/H) at the front of the carton.

  2. Cut the carton seal and open the carton.

  3.  

     

    NOTICE! Housing damage by pulling on the housing

  4. The machine stands on a separate insert. Grasp the insert by the handle and pull the machine out of the carton.
  5. Cut the fastener of the blue transport protection cover on the front of the machine.

  6. Pull the transport protection cover backwards over the machine and press it down on all sides until the top of the bottom cushion is exposed.

  7.  

     

  8. Remove the accessory pad from the machine.

  9. Remove the upper padding from the machine.
  10. Open the working chamber door.

  11. Remove the support pad under the working chamber door.

  12.  

     

     

  13. Reach into the left and right recessed grips in the lower padding.

    Slide your hands under the machine until you have a firm grip on the underside of the machine.

     

  14. Lift the machine out of the padding.

    1. Place the machine on a surface that can carry the machine weight.

       

       

    2. NOTICE! Make sure that the following safety distances are always maintained.

      Top view

      Blue area: workspace

      Side view

       

  15. Pull the protective housing cover upwards off the machine.

  16. Remove the transport lock from the working chamber:

    1. Push the plastic dowel downwards out of the transport lock.

    2. Pull the lower part of the transport lock out of the machine.

    3. Tilt the upper part down and remove it.

  17.  

     

     

  18. Close the working chamber door.

    Commissioning is only possible with the working chamber door closed.

  19.  

  20. Keep all parts of the transport lock and the packing set for possible service returns.

     

What's next?

If you want to proceed directly with the installation:

Checking the scope of delivery

If you want to get an overview of the machine first:

Machine overview